Rosa
Client
Total E&P Angola
ROLE
Construction of new units in module form and management of all activities to be carried out on the Girassol FPSO
LOCATION
Rosa field – Angola
DATE
2005/2007
CLIENT SPECIFICS
Rosa is located at 15km from the Girassol FPSO. It was the very first oil field of this size in deep waters to be linked to a FPSO.
Purpose: to enable Total, who operates the Girassol field at 150Km off the Angolan coast, to pump crude oil from a second underwater field (Rosa) from the same floating unit.
PONTICELLI’S CHALLENGES
It was the first time that we carried out such a large offshore project without stopping production.
Arrival in force in Angola
Ponticelli was in charge of all the works “above sea level”
SCOPE OF SERVICES
Scope:
- Fabrication, installation and integration of 6 modules on the FPSO.
- The new facilities were made up of 6 modules weighing a total of 6,000 t, 4 of which were built in France at Fos-sur-Mer, the other two were built in Angola.
KEY FIGURES
35
months of duration
3,000,000
man-hours
1,500
peak personnel
€430m
turnover
Projects
No Results Found
The page you requested could not be found. Try refining your search, or use the navigation above to locate the post.
Your Ponticelli contact
Philippe Braure
1 rue Lilienthal - Emerainville - BP 79
77312 Marne-la-Vallée Cedex 2
France
+33 (0)1 64 11 11 64
Contact-us