Barracuda 1 to 4 – nuclear boiler room and conventional zones

Client

NAVAL GROUP

ROLE

Ponticelli is in charge of the assembly and installation of piping on the submarine in the nuclear boiler room and conventional zones, and is also participating in the preparation of the intervention documents.

LOCATION

Cherbourg

DATE

2016/2020

CLIENT SPECIFICS

Naval Group set targets in terms of quality-safety-environment. A significant challenge in terms of budget in a context consisting of co-activity and strict schedule milestones.

PONTICELLI’S CHALLENGES

Schedules that have to be strictly maintained with milestones concerning co-activity, working hours adapted to schedule and milestones, maintaining cleanliness of all the pipe lines that are to be installed, strict welding quality requirements with non-destructive testing, responsiveness to resource needs which change according to the works progress and schedule.

SCOPE

  • BARRACUDA 1 & 2 in progress
  • BARRACUDA 3 & 4 to be launched before the end of 2018

KEY FIGURES

50,000
man-hours per year


40 à 45
people deployed
including 10 engineer-technicians

Projects

Your Ponticelli contact

Vincent Ladougne

Vincent Ladougne

1 rue Lilienthal - Emerainville - BP 79
77312 Marne-la-Vallée Cedex 2
France
+33 (0)1 64 11 11 64

Contact-us

    For more information about your rights and how to exercise them, particularly the withdrawal of your consent for the use of the information provided in this form, please refer to our privacy policy.