Starting up of a turbine on the Bimont dam
Client
Société du Canal de Provence
ROLE
Mechanical maintenance on the FRANCIS turbine on the BIMONT dam
LOCATION
Saint-Marc-Jaumegarde (Dpt 13) / France
DATE
2012
CLIENT SPECIFICS
General valve inspection and rapid rehabilitation of the installation
Important loss of energy while the turbine was shut down
PONTICELLI’S CHALLENGES
- Respect the deadline for installation start-up
- Access to the apparatus under difficult conditions
- Working in synergy between the mechanical and machining teams
SCOPE
- Dismantling
- Expertise
- Recommendations
- Re-assembly
- Testing
- Start-up
CHIFFRES CLÉS
825 kW
DUMONT turbo-generator
2,300
l/s at 42 m
750
rpm
Projects
No Results Found
The page you requested could not be found. Try refining your search, or use the navigation above to locate the post.
Your Ponticelli contact
Vincent Ladougne
1 rue Lilienthal - Emerainville - BP 79
77312 Marne-la-Vallée Cedex 2
France
+33 (0)1 64 11 11 64
Contact-us