Renovation of the penstock at Bens

Client

BATTAGLINO
Project Management: HYDROSTADIUM
Commissioned by: EDF

ROLE

Boiler works

LOCATION

EDF power plant at Bens – France (Dpt 73)

DATE

Project in progress

CLIENT SPECIFICS

The penstock at Bens was put into service in 1959. To eliminate corrosion problems EDF has started important renovation works to extend the plant’s operating life span by 20 years. This requires a 7-month production shutdown without any major maintenance works.

PONTICELLI’S CHALLENGES

This worksite requires Ponticelli’s skills in site boiler works (access roads, sectioning, welding works) in steep work areas with poor access (helicopter transportation). Production of new components in our boiler works workshop in Echirolles (fabrication of expansion joints, penstock section fabrication)

INTERVENTIONS

  • 900 mm shaft diameter
  • 1,985 linear metres and 535 m drop height
  • 4 expansion joints to be designed, produced and replaced
  • 11 work stations dispersed along the linear
  • About 50 helicopter trips for our equipment

CHIFFRES CLÉS

50
helicopter trips
for our equipment


11
work stations dispersed along the linear

Projects

Your Ponticelli contact

Vincent Ladougne

Vincent Ladougne

1 rue Lilienthal - Emerainville - BP 79
77312 Marne-la-Vallée Cedex 2
France
+33 (0)1 64 11 11 64

Contact-us

    For more information about your rights and how to exercise them, particularly the withdrawal of your consent for the use of the information provided in this form, please refer to our privacy policy.